Website projects rarely fail on design; they fail on waiting. Waiting for assets, waiting for homepage sign-off, waiting for content entry. Splitting the process into milestones with defined deliverables makes it obvious who must act now, and delays drop sharply.
Milestone 0: kickoff (1 day)
Confirm contract and payment, name the contact on each side, open a project group, agree communication frequency. The output is a schedule listing owner and deadline for every milestone.
Milestone 1: base assets (2-3 days)
The client supplies company information, product categories with detailed specs for one or two products each, contact details, logo and brand assets. This is the most common blocker in any project, so put the submission deadline in the contract.
Milestones 2-4: homepage design (about 8 working days)
The designer proposes, the client comments, the style is signed off. Key rule: sign-off covers structure and style only, with copy and images editable later; otherwise every image change restarts the process.
Milestones 5-7: inner page design (about 8 working days)
Design templates per section: product list, product detail, news list, news detail, about, contact. Again design, revise, confirm. Development starts only after inner pages are approved.
Milestone 8: development (about 15-18 working days)
Full layout and build, while the client prepares all product data and copy. This is where development waits on content, so send the asset list early.
Milestones 9-10: staging and acceptance (about 4 working days)
Deploy to a staging server with a reachable address and check item by item against the acceptance sheet: page completeness, form submission, mobile display, load speed and SEO basics. Collect issues into one list and fix in a single pass rather than adding requests while fixing.
Milestone 11: content entry (3 working days)
Enter company profile, certificates, news, product images and details, then run site-wide link and TDK checks. This shapes the first impression after launch and is the step most often compressed.
Milestone 12: launch and training (1 day)
Bind the domain, configure SSL, submit the sitemap, enable analytics, then train on the CMS: publishing news, adding products, changing banners. Record the session so future staff can watch it.
Two causes of delay and how to counter them
First, assets arrive late, so write the asset list and deadline into the contract along with a clause that the schedule shifts if assets are late. Second, scope creep, so set change windows: collect requests before each stage ends, and only fix bugs within a stage rather than adding features. With both enforced, ten weeks is a normal delivery.